Art Gallery and Museum Development Outturn
13/02/2014 - The Wilson - Development Project Outturn Briefing Report
RESOLVED that :
- Authority be delegated to the Executive Director / Director of Resources to settle the contract sum with the main contractor as set out in Appendix 2 (Exempt).
- The additional underwriting of the AG&M development project in the sum of £360,000 be supported and that Council be recommended to approve the budgetary provision for this.