Issue - decisions

Public realm improvements to High Street (east)

06/02/2018 - Public realm improvements to High Street (East)

1.    To adopt the mid-range design option for the first phase of public realm improvements to High Street (east) between Rodney Road and Cambray Place at an estimated construction cost of £696,000 (based on latest cost plan). The set of paving materials being;

 

  1. Ethically sourced Yorkstone equivalent blocks for pedestrian space, vehicle space and event space;
  2. Pre cast concrete Conservation kerb for kerb edgings

 

2.    To agree that subsequent stages of the works may transition to alternative sets of materials beyond Cambray Place.