Decision details
Appointment of Sustainability Consultants, Monkscroft School Site
Decision Maker: Director of Finance and Assets and Deputy Section 151 Officer - Gemma Bell
Decision status: Recommendations Approved
Is Key decision?: No
Is subject to call in?: No
Decision:
To accept the fee proposal received from
Calfordseadon ltd to act as Sustainability consultants for the
redevelopment of the former Monkscroft School Site and for CBC to
enter contract with them.
Reasons for the decision:
In recent months we have been working to
appoint the consultants required to work as a wider design team
with the intention of submitting a planning application for the
site later this year.
For the appointment of the Sustainability Consultant the project
team explored a range of potential procurement options and
Frameworks. It was collectively agreed with Publica and One Legal
that the NHSSBS Framework offered the most suitable list of
potential suppliers on the Framework that fit the required schedule
of services, etc.
Calfordseadon Limited was identified as a suitable supplier under
the relevant and available lot (lot 5) with the range of expertise
required within the core services for MEP, they provide
collaborative working as a key to the successful delivery of their
services. They can provide design in support of projects and in
delivering innovative solutions.
Therefore, the scope of services for a Mechanical, Electrical and
Plumbing Engineering consultants was procured through the
framework, NHSSBS, and as the framework is a public sector
framework, CBC can access the appointment it.
The proposal is to enter contract with Calfordseadon Limited via a
direct call off permissible via the NHS Framework and they are to
act as MEP Engineering consultants for the redevelopment of the
former Monkscroft School site to provide new affordable homes to
develop the site from concept design stage at RIBA Stage 2 through
to RIBA Stage 4a.
Alternative options considered:
An alternative option would have been to
procure the design and technical services as one multi-disciplinary
appointment. However, this scenario was assessed, and found that a
project of this complexity would need to have independent
consultants appointed to develop and support the design process
– this approach was rejected earlier in the procurement
planning process.
Declarations: None.
Other reasons / organisations consulted
We have worked with Publica and One Legal (OL)
throughout the procurement and tendering process, and internal
consultation within the development team along with support from
the externally appointed Project Management team, Henry
Riley.
We received feedback from both Publica and OL supporting us in
using NHSSBS framework for the direct award / call-off process
permissible under this framework.
The principle of redeveloping the site is supported by the
overarching governance bodies for new supply comprising CBC/CBH
Senior Officers at SHDG and Cabinet Member Housing Working
Group.
We have consulted with CBC’s sustainability lead around the
scope of services.
Contact: Gemma Bell, Director of Finance and Assets and Deputy S151 Officer Email: [email protected].
Publication date: 16/04/2024
Date of decision: 02/04/2024